• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jun 2018 - Aug 2019
  • Estimated project cost $680,000
  • Australian Government contribution $213,251
  • Local Council/Shire Baw Baw Shire Council
  • State VIC

Project description

Extensive pavement failures within the area and isolated damage to existing kerb and channel and history of flooding.

Replacement of damaged lengths of existing kerb and channel, widen road pavement along east side including installation of new kerb and channel, reconstruct the existing road pavement and provide an asphalt overlay.

Total cost of proposed project is $680,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.