• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2017 - Dec 2017
  • Estimated project cost $265,625
  • Australian Government contribution $265,625
  • Local Council/Shire Penrith City Council
  • State NSW

Project description

Borrowdale Way was constructed approximately in 1980 and the road is full of patching and showing failures due to the increasing heavy vehicle on Borrowdale Way

It is proposed to reconstruct the pavement with deeplift asphalt to a depth of 150mm for approximately 150 meters long to a width of 12 meters

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.