• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jul 2017 - Jun 2018
  • Estimated project cost $856,657
  • Australian Government contribution $856,657
  • Local Council/Shire Newcastle City Council
  • State NSW

Project description

This project is to replace and upgrade the existing pavement on John T Bell Drive. This is to reduce improve asset service life and ride quality on school and public bus routes. This will lower current and future maintenance costs and provide an acceptable Level of Service for this asset.

Stage 2 Works following on from Stage 1 which was McNaughton Ave to Grange Ave. Design and construction to rehabilitate approximately 250m of 12m wide road pavement and K&G. Works include pavement, subsoil drainage, stormwater drainage.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.