• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2018 - Jun 2018
  • Estimated project cost $66,344
  • Australian Government contribution $66,344
  • Local Council/Shire King Island Council
  • State TAS

Project description

There was a narrow section of the South Road emerging from Old Grassy Road making Old Grassy Road a collector of South Road. There is a need to make a T intersection to adjust the road hierarchy to make South Road as the main road. There is also a need to improve the turning radius at the T intersection for haulage trucks.

The cost associated will include the ripping off the existing deteriorated wearing course, widening the road at corners to the full depth and then sealing the intersection. It will also include line marking and signage.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.