• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jan 2019 - Apr 2019
  • Estimated project cost $26,883
  • Australian Government contribution $26,883
  • Local Council/Shire Shire of Coolgardie
  • State WA

Project description

Old and narrow bitumen surface with concrete kerbing in poor condition

Widen the sweeps, cement stabilise, apply a two coat bitumen surface and replace concrete edge kerbing

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.