- Funding program Major Project Business Case
- Status Completed
- Transport mode Rail
- Expected start/finish Early 2020 - Early 2021
- Estimated project cost $16,000,000
- Australian Government contribution $8,000,000
- Local Council/Shire Kiama Municipal Council,Council of the City of Shellharbour,Shoalhaven City Council,Sutherland Shire Council,The Council of the City of Sydney,Wollongong City Council
- State NSW
- Corridor Sydney - Wollongong
Project description
The project developed a strategic business case that investigated options to provide faster passenger rail services from Sydney to Bomaderry via Wollongong.
Benefits
The project determined the economic, environmental and social costs and benefits of improved passenger rail services from Sydney to Bomaderry via Wollongong.
Funding
The cost of the strategic business case was $16 million. The Australian Government contributed $8 million (capped) and the New South Wales Government $8 million.
Timetable
The strategic business case commenced on 13 March 2020 and was completed on 5 March 2021.
Project last updated:
Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.