• Funding program Investment Road and Rail Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Early 2022 - Early 2023
  • Estimated project cost $10,960,000
  • Australian Government contribution $5,480,000
  • Local Council/Shire Nillumbik Shire Council
  • State VIC

Project description

The project increased the capacity of commuter car parking facilities through construction of 102 new car spaces at Eltham Station by extending the existing at-grade carpark.

Benefits

This project supported public transport usage and efficiency by improving park and ride facilities at this location.

Funding

The Australian and Victorian governments each contributed $5.48 million.

Timetable

The project commenced construction in April 2022 and was completed in March 2023.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.