• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Aug 2019 - Mar 2020
  • Estimated project cost $635,555
  • Australian Government contribution $635,000
  • State QLD

Project description

The existing road is very rough and requires renewal to meet current level of service standards.

Reshape exsting pavement, overlay with 125 - 150mm of new pavement, bitumen seal.

Total cost of proposed project is $635,555

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.