- Funding program Roads to Recovery Program
- Status Completed
- Transport mode Road
- Expected start/finish Jul 2019 - Dec 2019
- Estimated project cost $925,000
- Australian Government contribution $620,261
- Local Council/Shire Burdekin Shire Council
- State QLD
Project description
Defects observed from Level 2 Inspections - Broken transverse stressing bars - Failure of deck wearing surface - Rubber bearings are severely split - Spalling on kerb units with exposed prestressing strand - No guardrail fittedMinor repairs to concrete components, resurfacing and sealing of carriageway, replacement of post tensioning bars. Repairs to headstocks and piers - Repairs to transverse stressing bars - Cut and seal all expansion joints - Replace wearing surface including water proofing membrane - Replace all guardrails - Repair bridge rails, posts and delineators - Minor drainage works on approaches - Repair concrete kerb spalling - Replace concrete sections on bridge approach - Removal of existing vegetation/debris
Total cost of proposed project is $925,000
Project last updated:
Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.