• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2019 - Jun 2020
  • Estimated project cost $340,544
  • Australian Government contribution $189,741
  • Local Council/Shire Mckinlay Shire Council
  • State QLD

Project description

Pavement failure in these sections of Road, also kerb and channel failure in sections allowing storm water egress to pavement

ch 0:068 km to 0:400 km x 6m wide stabilisation of pavement, 2 coat seal on primer seal. Kerb and channel ch 0:430 km to ch 0:530 km. Then ch 0:400 km to 0:800 km x 7m wide stabilisation of pavement, 2 coat seal on primer. Then ch 0:900 km to ch 0:950 km x 3m stabilisation of pavement, 2 coat seal on primer. Then ch 1:100 km to ch 1:120 km x 3m stabilisation of pavement, 2 coat seal on primer.

Total cost of proposed project is $340,544

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.