• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2020 - Apr 2020
  • Estimated project cost $106,400
  • Australian Government contribution $106,400
  • Local Council/Shire Gunnedah Shire Council
  • State NSW

Project description

Due to increasing activity of heavy vehicles, the pavement thickness and type of material used is inadequate, it is causing safety issues with all stakeholders including the school bus service

Re-sheet pavement to a depth of 100mm to improved strength and road surface to improve safety for all stakeholders

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.