• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Nov 2019 - Dec 2019
  • Estimated project cost $250,431
  • Australian Government contribution $250,431
  • Local Council/Shire Campbelltown City Council
  • State NSW

Project description

The road pavement is affected with significant levels of crocodile cracking, pumping of fines and rutting. The roughness is also very high.

The road section will be rehabilitated with Cement stabilisation followed by seal and hot-mix asphalt. The length of the section is 492m, width is 10.1m and area is 4973m2.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.