• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2019 - May 2020
  • Estimated project cost $449,700
  • Australian Government contribution $449,700
  • Local Council/Shire Lachlan Council
  • State NSW

Project description

The narrow seal on Boeramble Road has reached the end of its Life. The unsealed shoulders were gravel resheeted in 2015 but traffic volumes have created problems with the unsealed shoulder and continual failure of the sealed surface dictates it is time to reconstruct and widen the pavement. The narrow pavement is a road safety problem.

The existing formation will be reconstructed and widened with a gravel overlay and the new formation will be sealed with a two coat seal.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.