• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jan 2020 - Jun 2020
  • Estimated project cost $76,928
  • Australian Government contribution $76,928
  • Local Council/Shire Shire of Dowerin
  • State WA

Project description

This section of road was reconstructed in 2016 and sealed with a cold emulsion seal. The cold emulsion seal has oxidized with severe cracking. Water is penetrating through the cracks in the bitumen seal causing pavement failures.

The pavement failures will be cement stabilized and sealed. Once all the failed sections repaired and sealed, the full section will be reseal with poly modified bitumen.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.