• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2020 - Mar 2021
  • Estimated project cost $1,560,000
  • Australian Government contribution $241,860
  • Local Council/Shire Wagga Wagga City Council
  • State NSW

Project description

Existing road is has numerous pot holes , cracking and uneven road surface and poor drainage making driving unsafe .

Trickle Flow drainage works/culvert replacement and pavement reconstruction of the for the length of road 2.439km and 8 metres wide

Total cost of proposed project is $1,560,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.