• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jul 2019 - Jun 2020
  • Estimated project cost $85,572
  • Australian Government contribution $85,572
  • Local Council/Shire Central Goldfields Shire Council
  • State VIC

Project description

Tullaroop Road 300 metres long and 10.5 metres wide and Bucknall Street 120 metres long and 10.5 metres wide, is a Rural Link Road intersection where the existing primer seal bitumen surface on the approaches has deteriorated causing severe stripping and potholes to the surface caused by slowing and turning heavy vehicles.

The existing surface approaches to the intersection along Tullaroop Road and Bucknall Street is to be asphalted with 40 mm thick heavy vehicle asphalt overlay and line marking.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.