• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2022 - Oct 2022
  • Estimated project cost $918,861
  • Australian Government contribution $918,861
  • Local Council/Shire Colac Otway Shire
  • State VIC

Project description

Weak pavement and wear of seal due to heavy vehicles as it is the timber harvesting route and situated within an industrial area.

Design and rehabilitation of the existing pavement, widening, installation of sections of kerb and channel and associated drainage and application of asphalt seal.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.