• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2020 - May 2020
  • Estimated project cost $62,418
  • Australian Government contribution $61,930
  • Local Council/Shire District Council of Mount Remarkable
  • State SA

Project description

The current drainage is insufficient for the stormwater to escape during significant rains which creates substantial damage to buildings and infrastructure. The upgrade to the road will improve the drainage by directing the flow of water down the road to eliminate road surface damage and the residents properties flooding.

Construct and seal 200m pavement full length, construct upright kerbing full length on northern side and install side entry pit and 40 meters of pipework.

Total cost of proposed project is $62,418

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.