• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish May 2020 - Jun 2020
  • Estimated project cost $214,208
  • Australian Government contribution $214,208
  • Local Council/Shire Local Government Association of the Northern Territory Inc
  • State NT

Project description

Lose of gravel causing pavement failure and bogs after rains. Heavy corregation at chainage 5km at corner.

Gravel sheeting 150mm compacted for 5.2 km and realignment and widening of road at chainage 5km.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.