• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2019 - Feb 2020
  • Estimated project cost $157,318
  • Australian Government contribution $157,318
  • Local Council/Shire Local Government Association of the Northern Territory Inc
  • State NT

Project description

Gravel road is narrow with line site at corner being of a safety concern. Floodway scours annually after rains.

Road to be widened from 6 meters to 8 meters in width for 2000meters, with clearing of vegetation. Gravel sheeting with a lift of 200mm in depth with associated drainage. Box out of floodway 10 meters by 15 meters with rock and gravel sheet and cement stabilisation.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.