• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2020 - May 2021
  • Estimated project cost $193,424
  • Australian Government contribution $50,000
  • Local Council/Shire Warrumbungle Shire Council
  • State NSW

Project description

The existing bitumen surface is narrow in width and the pavement has failed, which has caused edge drop offs and a deformed surface

Widen the pavement by overlaying existing surface with 100mm compacted road base and increasing width of bitumen seal by 3 metres.

Total cost of proposed project is $193,424

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.