• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2020 - Jun 2021
  • Estimated project cost $1,200,000
  • Australian Government contribution $654,945
  • Local Council/Shire Kentish Council
  • State TAS

Project description

Kerbs and footpaths have displaced and broken allowing water ingress into the pavement and resultant failures of the nearby sealed parking lanes. Main Street also forms the main road through Sheffield and significant works are required to improve the general amenity of the area for locals and visitors.

Replace the kerbs, renew the pavement and asphalting of the parking lanes on both sides of the road. Introduce street trees and replace the footpaths.

Total cost of proposed project is $1,200,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.