• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jun 2022 - Jun 2022
  • Estimated project cost $80,000
  • Australian Government contribution $80,000
  • Local Council/Shire Town of Port Hedland
  • State WA

Project description

Yandeyarra Road is the sole access for the Yandeyarra Community. The road is crossed by the Yule River and several small creeks. Access is often restricted after rain fall events due to inadequate creek crossings.

Floodway, install new concrete slab total 70m x 4 @200mm thick with double SL72 mesh.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.