• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jul 2019 - Apr 2020
  • Estimated project cost $2,350,000
  • Australian Government contribution $439,447
  • Local Council/Shire Cobar Shire Council
  • State NSW

Project description

Grain Road is heavily used during harvest season with many tonnes of grain being transported along this route to the Euabalong West grain rail transport facility. The unsealed sections of road add to the cost of transport and cause accessibility issues for local farmers during periods of inclement weather.

Construct approximately 12km of road (shape formation, stabilise sub-base pavement layer, import gravel and stabilise base pavement layer, and seal)

Total cost of proposed project is $2,350,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.