• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Dec 2019 - Apr 2021
  • Estimated project cost $2,517,709
  • Australian Government contribution $298,358
  • State NSW

Project description

Distorted road surface, narrow and winding pavement that requires realignment

Realign and widen 2000 metres of Burra Road by way of full road reconstruction. 300mm DGB20 pavement, realigning the exsiting substandard alignment and apply a 10mm primerseal.

Total cost of proposed project is $2,517,709

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.