• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2019 - Feb 2020
  • Estimated project cost $200,000
  • Australian Government contribution $200,000
  • Local Council/Shire Wellington Shire Council
  • State VIC

Project description

Existing gravel road formation is in poor condition with consistent corrugation and overgrown vegetation.

3.65km stretch of road to be regraded and resheeted with rock. Roadside vegetation to be cut back, table drains reformed and culverts crossing the road to be lengthened with end walls fitted.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.