• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2020 - Jun 2020
  • Estimated project cost $73,124
  • Australian Government contribution $73,124
  • Local Council/Shire Walcha Council
  • State NSW

Project description

Normal Deterioration of the road due to soft underlying pavement

Heavy patch pavement 800m long x 3.5m wide section with 200 m thick gravel, C170 bitumen binder, 10 mm and 7 mm precoated aggregate seal.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.