• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Dec 2019 - May 2020
  • Estimated project cost $580,027
  • Australian Government contribution $580,000
  • Local Council/Shire Mitchell Shire Council
  • State VIC

Project description

Failed pavement and dilapidated Kerb and Channel

Full Road rehabilitation including new Kerb and Channel (West side of the road)

Total cost of proposed project is $580,027

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.