• Funding program Investment Road and Rail Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mid 2017 - Early 2021
  • Estimated project cost $7,760,000
  • Australian Government contribution $5,760,000
  • State NSW

Project description

Upgrade of Badgally Road between Eagle Vale Drive and North Steyne Road, including:

  • widening a section of Badgally Road from 2 lanes to 4 lanes
  • installation of kerb and guttering
  • installation of directional signage
  • central concrete medians
  • provision of indented bus bay
  • off road shared pathway
  • new traffic control signals at the intersection of Badgally Road with Clydesdale Drive and Badgally Road with North Steyne Road

Benefits

The project is expected to improve traffic flows, reduce congestion, and improve capacity and access to the broader arterial road network.

Funding

Australian Government is contributing up to $5.8 million towards the project.

Timetable

Construction commenced mid 2017 and was completed in March 2021.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.