- Funding program Investment Road and Rail Program
- Status Completed
- Transport mode Road
- Expected start/finish Late 2020 - Late 2022
- Estimated project cost $7,475,026
- Australian Government contribution $7,475,026
- Local Council/Shire Campbelltown City Council
- State NSW
Project description
This project will upgrade the intersections between Raby Road and Spitfire Drive and Raby Road and Eagle Vale Drive.
Benefits
The project is expected to:
- Improved existing alternate link between Campbelltown City Council and the new Western Sydney Airport
- Improved travel time between the suburbs of Campbelltown
- Improved traffic flow and enhanced safety for all road users
- Reduction in fuel consumption and greenhouse gas emissions
- Improved public transport linkage to the commuter rail network from the south coast and beyond to the proposed airport
Funding
The Australian Government funding is capped at $7.5 million.
Timetable
Construction commenced in late 2020 and was completed in late 2022.
Project last updated:
Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.