• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2020 - Jun 2021
  • Estimated project cost $1,597,448
  • Australian Government contribution $1,550,000
  • Local Council/Shire Toowoomba Regional Council
  • State QLD

Project description

This section of road (approx. 1.3 Km) has been identified by the Toowoomba Regional Council's asset management system as a section of the road network to be rehabilitated. This road is classified as a regional arterial and significant link in the local road network it current has Approx. 2700 VPD with a significate percentage of heavy vehicles (10%).

Rehabilitate the pavement to a two lane standard (8m Seal on 8.5m formation), including pavement widening and adjustment to intersections to cater for heavy vehicles.

Total cost of proposed project is $1,597,448

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.