• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jun 2021 - Dec 2021
  • Estimated project cost $98,700
  • Australian Government contribution $98,700
  • Local Council/Shire Lord Howe Island Board
  • State NSW

Project description

Existing seal surface severely cracked and rutted from general traffic. Large potholes present. On commencing, very little existing road base has been found - original road constructed on compacted local soil. This has been severely impacted by tree roots. Requires significant additional road base and work.

Reconstruct road. Remove tree roots and soft material. Add new road base and tree root guard, improve road camber and drainage. Compact. Apply 10/7 bitumen seal.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.