• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Dec 2019 - May 2020
  • Estimated project cost $336,364
  • Australian Government contribution $335,000
  • State QLD

Project description

The existing unsealed road has poor gavel coverage and is corrugated which negatively effects the safety of users of the road users.

Reshape the existing gravel, overlay with 100 - 150mm of new pavement material

Total cost of proposed project is $336,364

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.