• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Apr 2020 - Apr 2024
  • Estimated project cost $915,737
  • Australian Government contribution $915,737
  • Local Council/Shire Narromine Shire Council
  • State NSW

Project description

major drainage and pavement issues and heavy vehicle access is restricted

Upgrade road from gravel to bitumen surface in places, widen road carriageway to 8m, installs large boxed culverts

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.