• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish May 2020 - Jan 2021
  • Estimated project cost $123,900
  • Australian Government contribution $72,668
  • Local Council/Shire Shire of Dowerin
  • State WA

Project description

Road is built over salt lakes and moisture is evident under the seal. Moisture has caused a subgrade failure with the pavement and seal breaking up with deep wheel rutting which is a safety risk to all road users.

Pavement will be removed and subgrade will be stabilized with cement and lime. Road base will be imported for the new pavement and cement stabilized, final trimmed and sealed.

Total cost of proposed project is $123,900

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.