• Funding program Investment Road and Rail Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Early 2020 - Mid 2020
  • Estimated project cost $3,000,000
  • Australian Government contribution $2,400,000
  • Local Council/Shire Shire of Northam
  • State WA
  • Corridor Perth - Adelaide

Project description

The project will replace Bridge 0604 in Coates Gully with a new culvert on the Great Eastern Highway (GEH), including drainage improvements. The bridge will be widened to a twelve metre formation, with approach roads widened to allow for safe tie-ins.

Benefits

  • Improve road safety for all road users
  • Improve efficiency and network reliability

Funding

The Australian Government has committed $2.4 million towards the $3.0 million project.

Timetable

Construction commenced in April 2020 and was completed in August 2020.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.