• Funding program Investment Road and Rail Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Early 2021 - Mid 2023
  • Estimated project cost $3,000,000
  • Australian Government contribution $1,500,000
  • Local Council/Shire Burnie City Council
  • State TAS

Project description

This project supplied, installed and commissioned approximately 200 new Electronic School Zone Speed Limit Signs along with a new Network Management System to manage the upgraded signs remotely.

Benefits

The project improved road safety for all road users.

Funding

The Australian and Tasmanian Governments contributed $1.5 million each to this project.

Timetable

Construction commenced in January 2021 and was completed in May 2023. 

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.