- Funding program Investment Road and Rail Program
- Status Completed
- Transport mode Road
- Expected start/finish October 2020 - Mid 2023
- Estimated project cost $19,500,000
- Australian Government contribution $15,600,000
- Local Council/Shire Logan City Council,Redland City Council
- State QLD
Project description
Targeted road safety improvements including audio tactile line markings, improved signage, removal of roadside hazards, road surface and shared path treatments, installation of turning lanes.
Benefits
Improved road safety for all road users.
Funding
The Australian Government has committed $15.6 million towards this project.
Timetable
The project commenced construction in October 2020, original package of works completed in October 2021. One additional package of works was added and was completed in August 2023.
Project last updated:
Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.