• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jan 2021 - Feb 2021
  • Estimated project cost $165,067
  • Australian Government contribution $165,067
  • Local Council/Shire Campbelltown City Council
  • State NSW

Project description

The road surface is more than 30 years old, oxidised and affected with moderate levels of ravelling and cracking. The length of the road section is 488m, width 11.2 m and proposed treatment area is 5466m2

The proposed treatment include heavy patching the isolated failed area first followed by inter layer rubber seal with hot-mix asphalt overlay.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.