• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2021 - Jun 2021
  • Estimated project cost $150,664
  • Australian Government contribution $150,664
  • Local Council/Shire Shire of Lake Grace
  • State WA

Project description

This section of the road is too narrow for heavy traffic, is very sandy with lots of blowouts and the drainage is clogged with silt and weeds. There are a few stone ridges in high spots along this section. Signage is missing.

This section of road will be widened and re-sheeted with gravel compacted to 150mm. The stone ridges will be shape corrected with additional gravel surfacing. The drains, backslopes and off-shoots will be cleared of silt and light vegetation. New signage and guideposts will be installed.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.