• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jan 2021 - May 2021
  • Estimated project cost $352,126
  • Australian Government contribution $253,602
  • Local Council/Shire Shire of Carnamah
  • State WA

Project description

Sections of the road require improvements to the drainage and the existing pavement is very thin, potholed and corrugated. The drainage needs to be improved and the pavement increased to provide a safe running surface.

It is proposed to reconstruct the roadside drainage and then gravel re-sheet 7.52 kilometers by 8 meters wide. This will give a finished pavement depth of 300 mm.

Total cost of proposed project is $352,126

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.