• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2022 - Jun 2022
  • Estimated project cost $17,979
  • Australian Government contribution $17,979
  • Local Council/Shire City of Bunbury
  • State WA

Project description

Seal surface was installed with a substandard material. The surface is brittle and breaking down, beginning to reveal the below pavement. Kerbing is cracked as has been sealed to its maximum height, leaving no kerb face to seal against. This road / route is used by the South Bunbury Primary School Education Support Centre Regional School Bus Service as their pick up and drop off location.

Replace kerbing. Profile existing seal, and reseal with new asphalt.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.