• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2020 - Apr 2021
  • Estimated project cost $510,253
  • Australian Government contribution $510,253
  • Local Council/Shire City of Knox
  • State VIC

Project description

The road surface has aged and failed in places and the kerb and channel has failed or settled.

Asphalt overlay of the road pavement and reconstruction of failed pavement areas along with reconstruction of kerb and channel and associated drainage. Laser Drive is approximately 670 metres with a mostly uniform pavement width of 11.9 metres.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.