• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Aug 2020 - Jun 2021
  • Estimated project cost $2,500,000
  • Australian Government contribution $175,000
  • Local Council/Shire Weddin Shire Council
  • State NSW

Project description

Stage 2 of the Main Street upgrade is to rectify road geometry. The Main Street has excessive crossfall, which disallows council to implement disabled parking for the aging demographic of Grenfell.

The project will comprise of: - Earthworks - Drainage Works - Road reconstruction - Sealing with a 14/7 mm Bitumen seal - line marking, guide posting

Total cost of proposed project is $2,500,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.