• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2020 - Jun 2022
  • Estimated project cost $116,633
  • Australian Government contribution $116,633
  • Local Council/Shire Shire of West Arthur
  • State WA

Project description

Pressure on this section of road, at intersection of Capercup North of turning heavy vehicles on to Darkan South road at below in incline.

Clear, construct a sliplane to alleviate pressure point

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.