• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2020 - Nov 2020
  • Estimated project cost $393,716
  • Australian Government contribution $393,716
  • Local Council/Shire Townsville City Council
  • State QLD

Project description

Existing seal is aged with cracking, deformation and old patches throughout. Due to the adjacent trees, this condition will only worsen in time if not treated.

Remove all existing kerbs and road pavements (full width), treat subgrade with lime stabilization (if required). Full road reconstruction including all kerb and channel.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.