• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2021 - Mar 2021
  • Estimated project cost $91,207
  • Australian Government contribution $91,207
  • Local Council/Shire Townsville City Council
  • State QLD

Project description

This section of the street has areas of kerbs in sub standard condition with failures in the adjacent pavement. The remainder of the chip sealed pavement appears OK, but applying a full width asphalt overlay will significantly extend the life of this asset.

Replace kerbs (201m) and complete digouts (268.5m2) to rectify the failed pavement areas in this section. The total area for digouts also allows for the additional pavement removal adjacent to the kerb replacements. On completion mill remaining edges and apply full width overlay and reinstate all kerb and pavement markings.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.