• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jul 2020 - Sep 2020
  • Estimated project cost $135,290
  • Australian Government contribution $135,290
  • Local Council/Shire Bland Shire Council
  • State NSW

Project description

This road has extensive failures such as rutting and potholes. It is not currently considered safe for road users and school bus operators.

It is planned to regravel some sections with 75mm compacted gravel, and wet grade other sections which only have lost shape and restore the table drains and mitre drains.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.