• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Aug 2020 - Apr 2022
  • Estimated project cost $831,015
  • Australian Government contribution $826,632
  • Local Council/Shire Mid-Western Regional Council
  • State NSW

Project description

Interesection does not function well and pavement is in poor condition

Construct a roundabout including new pavement and concrete centre dome with concrete splitter isalnds and pedsetrian blisters

Total cost of proposed project is $831,015

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.