• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2020 - Jun 2021
  • Estimated project cost $53,380
  • Australian Government contribution $53,380
  • State QLD

Project description

This unsealed section of Ritha street from the intersection of Manchkunchan street is formed from Sand & Shellgrit and requires constant upgrading / maintenance. Council is wishing to continue the paving from the intersection of Manchkunchan street so as to control the fine power dust during the dry season and soil erosion during the wet season. There are currently 9 homes within this stretch of road heavily effected by the dust created by the local traffic.

Pave an unsealed section of Ritha street (approx 48mtrs) Resurface road base, sub-grade preparations & lay 212mm x 390mm Adbri Pavers with 0.400mm of concrete edging restraint on both road sides from Manchkunchan intersection up to and including approx 48mtrs in length

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.